The Latest Update on Avondale Road - 12/16/09
We have been informed by the County that grinding on the test segment of Avondale, south of 151st Street, is expected to take place by March 2010.
The panel repairs and replacement on that segment were completed last fall, but grinding was postponed when a new grinding contractor needed to be secured. The grinding contract is expected to be advertised on December 17th and the bids will open January 5th. The County estimates that it will take 2 possibly 3 months from the opening of the bids to starting work on Avondale.
Meanwhile, the County maintenance department has completed an asphalt patch on a short segment north of 151st Street to repair 2 severely damaged panels which were causing a significant safety and noise problem.
{ 0 comments… add one now }
Kick things off by filling out the form below ↓
Leave a Comment